1. Kronotex flooring
can of course be installed with full-surface
gluing. However, slab surface properties must be
determined with extreme precision beforehand, and
it must also be decided precisely hich
professional preparative procedures need to be
performed (application of an undercoat, puttying,
and sanding). According to the DIN 18202 standards
for evenness, shown in Table 3, unevenness of >
2 mm per 1 m must be eliminated.
2. Always make sure that the
underlying slab is absolutely dry, even, stable
and and clean. Existing allowances for movement in
the structure must be retained at the same places
and with the same degree of movement. Use a
polyurethane adhesive for full-surface gluing. D3
adhesive must also be applied to tongue-and-groove
joints (as described above) in full
surface-gluing.
Please consult a
qualified flooring installer!
Important ! ! !
Do not use
full-surface gluing with Kronotex laminate
flooring in the presence of underfloor heating.